The project at Holy Innocents Church was a joint venture between our Scaffolding Department and our Church and Conservation Department.
An internal birdcage was utilised in order to gain access to the areas that needed repairing. Meanwhile our rope access team boarded up one of the windows to enable the poles to be carried inside. The main issues the scaffolding department had was unlike most sites, the majority of the materials had to be passed through small windows. This meant standard techniques of offloading could not be used. Our team managed to get around this by passing the beams through small windows and managed to erect the entire scaffold in a relatively small space! |